Pune Possession Tracker: MahaRERA Completion Dates
The Pune Possession Tracker shows what MahaRERA’s own record says about the projects we audit โ the registered completion deadline, whether the builder has filed an extension, and how the August 2026 blanket order changes the date. Every figure here was read off the MahaRERA portal by us, not copied from a listing site.
Why this exists. A sales executive quotes you a possession date from a brochure. MahaRERA holds a different date โ the one the builder is legally committed to. Those two drift apart, and nobody is obliged to tell you. This page closes that gap for the projects we cover.
8 of 8 projects verified on the MahaRERA portal on 13 September 2026. Of those, 5 show a registration validity date that has already passed โ which means the registered completion deadline has expired without a later extension visible on the portal. That is not proof a project is in trouble, and it is not an accusation against any builder: promoters often register a later phase separately, and the portal record can lag. It is a question worth asking before you pay a booking amount.
The tracker
| Project | MahaRERA no. | Promoter on the record | Registered completion | Extension filed | After Aug 2026 order | Verified |
|---|---|---|---|---|---|---|
| Kalpataru Jade Skyline registered as: Kalpataru Jade Skyline | P52100033791 | Astrum Developments Private Limited | 31/12/2026 | No | 30/04/2027 | 2026-09-11 |
| Mantra Mirari registered as: Mantra Mirari Phase 2 later phase on sale: Mantra Mirari Phase 3 (P52100049704), completion 30/06/2026 โ also lapsed | P52100032842 | Mantra Residences Mundhwa Private Limited | 30/06/2026 lapsed | No | 30/10/2026 | 2026-09-12 |
| Mantra Monarch registered as: MANTRA MONARCH PHASE 1 later phase on sale: Mantra Monarch Phase 3 (P52100024918), completion 30/06/2026 โ also lapsed | P52100023453 | Mantra Kingdom Private Limited | 30/06/2026 lapsed | No | 30/10/2026 | 2026-09-12 |
| Majestique Towers registered as: MAJESTIQUE TOWERS EAST PHASE 1 later phase on sale: Majestique Towers East Phase-7 (P52100078306), completion 31/12/2028 | P52100015020 | M/s. Sharad Shree Enterprises | 30/12/2024 extended from 31/12/2022 lapsed | Yes | order does not apply | 2026-09-12 |
| Godrej Hillside 3 registered as: Godrej Hillside 3 | P52100050939 | Mahalunge Township Developers Private Limited | 28/02/2028 | No | 28/06/2028 | 2026-09-12 |
| Godrej Park Ridge registered as: Godrej Parkridge | P52100028310 | Manjari Housing Projects LLP | 30/09/2025 lapsed | No | order does not apply | 2026-09-12 |
| Godrej Emerald Waters registered as: Godrej Emerald Waters | P52100051200 | Godrej Properties Limited | 28/02/2029 | Yes | 28/06/2029 | 2026-09-12 |
| VTP Purvanchal registered as: Purvanchal Phase1 AB later phase on sale: Purvanchal F Building (P52100021535), completion 30/06/2024 โ also lapsed | P52100001109 | VTP Corpartion LLP (sic) | 29/12/2022 extended from 30/06/2021 lapsed | Yes | order does not apply | 2026-09-12 |
| Lodha Palais registered as: Kothrud Pune -Tower A and B | PR1260002400041 | Lodha Developers Limited | 30/09/2029 | No | 30/01/2030 | 2026-09-13 |
| Lodha Camelot registered as: Kharadi New Project – Tower 1 | PR1260002501386 | Lodha Developers Limited | 31/03/2030 | No | 31/07/2030 | 2026-09-13 |
Not yet on this table
- Lodha Massimo (PR1261012400049) โ The MahaRERA number published for this project resolves to โPune Baner Project โ Tower 4 and 5โ, registered by Goel Ganga Ventures India Pvt Ltd โ not Lodha. We are checking that with the builder before we list it here. If you are being sold this project, ask for the registration number in writing and check it on the MahaRERA portal yourself.
- Kolte Patil Life Republic โ Registered sector by sector โ 33 separate MahaRERA registrations, with no single registration covering the township. Tell us which sector or avenue you are buying in and we will pull that specific record.
What the columns mean
- Registered name โ projects are often registered under a different or phased name (for example “Phase 1”, “East Phase 1”). If the name on the brochure is not the name on the certificate, ask which registration covers the tower you are buying in.
- Registered completion โ the end date printed on the MahaRERA registration certificate (Form C): “registration shall be valid for a period commencing from โฆ and ending with โฆ”. This is the deadline, not a promise of handover.
- Extension filed โ whether the promoter has an extension certificate on the portal record. Repeated extensions beyond the regulator-wide ones are the signal worth paying attention to.
- After the Aug 2026 order โ MahaRERA’s blanket four-month extension, applied where the project qualifies. See below.
The August 2026 four-month extension
On 7 August 2026 MahaRERA granted an automatic four-month extension to registered projects, invoking force majeure over the conflict in West Asia. It applies to projects whose completion, revised completion or extended completion date falls on or after 28 February 2026. Projects registered on or after 1 August 2026 are not covered. Promoters did not have to apply, and the blanket order does not create a project-level extension certificate โ so a project can show “no extension filed” and still have four extra months.
A regulator-wide extension is not the same as a builder running late. Both show up on the record, and they mean different things. A few months is explained by the order. Years are not.
Check any project yourself, in five minutes
- Go to maharera.maharashtra.gov.in โ Search Project.
- Type the registration number (it starts with P5 and appears on every legitimate advertisement), or the project name.
- On the result card, open the Certificate and read the line beginning “registration shall be valid for a period commencing from”.
- Check whether an Extension Certificate exists, and how many.
- Read the quarterly progress updates โ promoters must file them.
We would rather you could do this without us. The full guide is here.
How this page is maintained
- Every row is read directly from the MahaRERA portal. Nothing is taken from 99acres, Housing, MagicBricks or a builder brochure.
- Each row carries the date we last verified it. We re-check monthly.
- Where we have not yet read a certificate ourselves, the cell says so. We do not print a date we have not seen.
- If you spot something that looks wrong, tell us and we will re-check it the same day.
Checking a specific project? Send us the name and we will pull its MahaRERA record โ original date, current date, extension history โ and tell you plainly what the pattern looks like. Free, and no obligation. WhatsApp us or use the free price check.
Published by Guiding Property, an independent MahaRERA-registered advisory (A031262401718). We are paid by the builder on completion and take no commission for steering buyers to any particular project. Dates on this page are registration deadlines from the MahaRERA record, not guarantees of handover.