Mantra Mirari Possession Date: Both Phases Have Lapsed
Both Mantra Mirari registrations we checked show a completion date of 30 June 2026 โ a date that has now passed. Phase 3 has an extension certificate on the portal, but MahaRERA’s own viewer will not open it. We tried twice on 12 and 13 September 2026. That means neither we nor you can currently read the revised date.
What the record shows
| Phase | MahaRERA number | Registration valid |
|---|---|---|
| Phase 1 | P52100030037 | Registered; certificate not yet read by us |
| Phase 2 | P52100032842 | 02/02/2022 โ 30/06/2026 ยท expired, no extension filed |
| Phase 3 | P52100049704 | 22/02/2023 โ 30/06/2026 ยท expired; extension certificate exists but will not load |
Promoter on the record: Mantra Residences Mundhwa Private Limited. Location: Mundhwa, pincode 411036.
The four-month order does apply here
Unlike older lapsed projects, Mirari’s 30 June 2026 date falls after the 28 February 2026 cut-off, so MahaRERA’s blanket order of 7 August 2026 carries it automatically to 30 October 2026 โ without any certificate being issued. How that order works.
So the honest position is: the registered deadline is now the end of October 2026, plus whatever the unreadable Phase 3 extension says.
What to do about the document that will not open
Ask the builder directly: “Please email me a copy of the Phase 3 extension certificate and the revised completion date.” A promoter has that document. If it cannot be produced, that is worth knowing before you pay a booking amount.
What this does not mean
This is not evidence that Mantra is in default. Registrations expire routinely while construction finishes, and a broken PDF on a government portal is a portal problem, not a builder problem. What it does mean is that the public record no longer shows you a clear, current completion date โ so get it in writing instead.
Check it yourself
- Go to maharera.maharashtra.gov.in โ Search Project.
- Search P52100049704 (Phase 3) or P52100032842 (Phase 2) โ search the number, not the name.
- Open the Certificate and read the “valid for a period commencing from โฆ ending with โฆ” line.
- Try the Extension Certificate icon. If it fails for you too, that confirms what we found.
Price context
Mirari is in Mundhwa, between Koregaon Park and Kharadi. We track Kharadi at โน9,800โ11,800 and Koregaon Park at โน14,500โ18,000 per sq ft carpet. Mundhwa sits between the two, so the quote you get should be read against that range โ and always converted to carpet area first.
Send us your phase and tower number. We will pull that exact registration, tell you the current deadline, and check your quote against our Mundhwa-belt rates. Free, and we show you the record. WhatsApp us ยท All projects we track
Verified from the MahaRERA portal, 12โ13 September 2026, by Guiding Property, an independent MahaRERA-registered advisory (A031262401718). Paid by the builder on completion; no commission for steering buyers to any project. Registration dates are legal deadlines, not promises of handover.