Majestique Towers Possession Date: Check Your Phase, Not the Project
If you are buying in Majestique Towers, the phase number matters more than the project name. Phase 1’s MahaRERA registration expired on 30 December 2024. Phase-7 โ the newest โ runs to 31 December 2028. Same project, same builder, completely different legal position. We read both certificates ourselves on 12โ13 September 2026.
Six registrations, not one
Majestique Towers East is registered phase by phase. A name search on MahaRERA returns six separate registrations from the same promoter, M/s. Sharad Shree Enterprises:
| Phase | MahaRERA number | Status on the record |
|---|---|---|
| East Phase 1 | P52100015020 | Original 22/01/2018โ31/12/2022, extended to 30/12/2024 โ expired |
| East Phase 2 | P52100015183 | Registered; certificate not yet read by us |
| East Phase 3 | P52100028815 | Registered; last updated March 2025 |
| East Phase 05 | P52100046709 | Registered |
| East Phase 6 | P52100053786 | Registered |
| East Phase-7 | P52100078306 | Valid 04/12/2024 โ 31/12/2028 |
Why this catches buyers out
A brochure says “Majestique Towers”. A portal listing says “Majestique Towers”. The MahaRERA certificate says “MAJESTIQUE TOWERS EAST PHASE 1” or “Majestique Towers East Phase-7” โ and those two carry different deadlines, four years apart.
If someone quotes you a possession date, it belongs to a specific registration. Ask which one covers your tower and your flat number. Every legitimate advertisement must carry the registration number for the phase being sold.
What the expired Phase 1 registration means
It means the registered deadline for that phase has passed and no later extension is visible on the portal. It is not evidence of a stalled project โ Phase 1 flats may well be complete and occupied, with the registration simply having run its course. What it does mean is that Phase 1 no longer has a live registered completion date on the public record.
Check your own tower in five minutes
- Get the registration number from the builder, in writing, for your specific tower.
- Search it at maharera.maharashtra.gov.in โ Search Project.
- Open the Certificate and read the “valid for a period commencing from โฆ ending with โฆ” line.
- Check whether an Extension Certificate exists, and how many.
Does the August 2026 four-month extension apply?
To Phase-7, yes โ its date is after 28 February 2026, so the blanket order carries it to 30 April 2029. To Phase 1, no: an expired 2024 date falls outside the order. How that order works.
Price context
Majestique Towers East sits in the 412207 pincode, on the WagholiโKharadi side. Our monthly carpet-rate bands for that belt: Wagholi โน6,000โ7,200 and Kharadi โน9,800โ11,800 per sq ft carpet. That spread is wide, so the exact location matters as much as the project.
Send us your tower number and we will check that exact registration free โ the real deadline, the extension history, and whether the price you have been quoted sits inside the band for that pocket. WhatsApp us ยท See all projects we track
Verified from the MahaRERA portal, 12โ13 September 2026, by Guiding Property, an independent MahaRERA-registered advisory (A031262401718). Paid by the builder on completion; no commission for steering buyers to any project. Registration dates are legal deadlines, not promises of handover.